Penjelasan @MYRapidKL Berhubung Masalah Tren Aliran Kelana Jaya @ShahrilMokhtar

RapidKL's Kelana Jaya Line LRT's operations for the Jelatek - Sri Rampai stretch has to opt for a degraded mode, where the trains are manually driven, following a technical hiccup in the signaling system.

Subsequently, the LRT service along this stretch is slow as the service has to be undertaken under a manual mode. A total of 29 four-car trains were deployed but the service remains slow and the crowd still have to wait longer to enter a train.

The technical hiccup situation arises following an exercise to remove an obsolete part of a signaling system as advised by a signaling system contractor appointed by RapidKL. 

The exercise, which started at 12am this morning and supervised by the signaling system contractor, encountered unexpected difficulties at 4:00am which disrupted the Automatic Train Operation System for the line.

Currently, RapidKL engineers are resolving the situation and the system is back to normal at 12:27pm today. RapidKL regrets any inconvenience arising from the situation.


Untuk maklumat lanjut, sila hubungi Pengurus Hal Ehwal Media PRASARANA Azhar Ghazali di talian 019-3837865 atau e-mel azharghazali@prasarana.com.my 
atau azharghazali99@gmail.com.

Sent by Maxis from my BlackBerry® smartphone
UNDILAH BARISAN NASIONAL ### VOTE FOR BARISAN NASIONAL

No comments:

SOAL HATI: ANTARA TUNTUTAN & IDAMAN